The Surveying Conundrum

  • Geographically defines the wellbore
  • Drilling safely
  • Achieves geological Objectives
  • Delivers engineering objectives
  • Time consuming
  • Increased pump cycles
  • Reducing borehole quality
  • Stuck pipe exposure

Measurement While Drilling — Current and Future

  • 1979
    • MWD measurement
    • 6 axis (3 accelerometers and 3 magnetometers)
    • Robust reliable and auditable
    • Survey taken when stationary
    • Time penalty
  • 2001
    • Continuous single-axis surveying
    • Improved trajectory control
    • Not definitive without static surveys
  • 2019
    • Continuous 6-axis surveying
    • Definitive survey taken while drilling
    • No “survey time”
    • Reduced pump cycles
    • Improved directional control

Continuous 6-Axis Surveys — Drilling Mode Surveys (DMS)

  • Continuous 6-axis surveying challenges
    • Phase compensation
    • Shock and vibration
    • Eddy currents

Continuous 6-Axis Surveys — Drilling Mode Survey Design Journey

  • Firmware
    • Single correction for all errors
    • Separating
      • Phase shift
      • Shock and vibration
      • Eddy current compensation
  • Hardware
    • Improve mag frequency response
    • Accelerometers already capable

...

View the entire Presentation:

Eliminating Rig Time from MWD Surveying

Ross Lowdon, M. Breen et al., Schlumberger

 

More from Meeting 49